Requirements
Any operational renewable energy generation system benefitting the PropertyPropertyMultifamily residential real estate securing the Mortgage Loan, including the fee simple or Leasehold interest, Improvements, and personal property (per the Uniform Commercial Code). or the BorrowerBorrowerPerson who is the obligor per the Note. must be:
- located on the PropertyPropertyMultifamily residential real estate securing the Mortgage Loan, including the fee simple or Leasehold interest, Improvements, and personal property (per the Uniform Commercial Code). ;
- comprised of a Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored…;
- BorrowerBorrowerPerson who is the obligor per the Note. -owned; and
- installed, or installation will begin, on or before the Mortgage Loan Origination DateMortgage Loan Origination DateDate you fund a Mortgage Loan to the Borrower. .
110.02 | |
|
Requirements
For any PropertyPropertyMultifamily residential real estate securing the Mortgage Loan, including the fee simple or Leasehold interest, Improvements, and personal property (per the Uniform Commercial Code). with an acceptable Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored…, you must ensure:
- All equipment, including energy storage, is located on the PropertyPropertyMultifamily residential real estate securing the Mortgage Loan, including the fee simple or Leasehold interest, Improvements, and personal property (per the Uniform Commercial Code). and owned by the BorrowerBorrowerPerson who is the obligor per the Note. .
- The BorrowerBorrowerPerson who is the obligor per the Note.
has all required permits, licenses, and certificates to comply with all utility tariffs and laws governing the
- generation,
- storage,
- transmission, and
- distribution of electricity.
- The PropertyPropertyMultifamily residential real estate securing the Mortgage Loan, including the fee simple or Leasehold interest, Improvements, and personal property (per the Uniform Commercial Code). will remain connected to the utility grid even if the Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored… output is sufficient for all of the Property'sProperty'sMultifamily residential real estate securing the Mortgage Loan, including the fee simple or Leasehold interest, Improvements, and personal property (per the Uniform Commercial Code). energy needs.
- The BorrowerBorrowerPerson who is the obligor per the Note. will not be characterized or regulated as a public utility.
- Any power generated from the Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored… that is not consumed or stored on-site is only sold to the local utility, not to any other third party.
- Any battery storage system is designed only for on-site uses (e.g., peak shaving), and the BorrowerBorrowerPerson who is the obligor per the Note. has not arranged for ancillary services with any utility or third party.
- The BorrowerBorrowerPerson who is the obligor per the Note. executes Modifications to Multifamily Loan and Security Agreement (Mortgage Loan with installed Solar Photovoltaic System) (Form 6270).
Guidance
You should engage legal counsel with solar photovoltaic system experience and state-specific knowledge to review all applicable local laws, contracts, and agreements regarding the Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored… installation and operation, including:
- the interconnection agreement with local distribution company or utility;
- any net metering agreements;
- engineering, procurement, and construction contracts or agreements;
- any Operating and Maintenance Agreements;
- notice of Permission to Operate (or similar document) provided by local distribution company or utility;
- any supplemental financing or financing incentives (e.g., grants, tax credits, etc.) used by the BorrowerBorrowerPerson who is the obligor per the Note. to finance the Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored… to determine if any competing liens or other restrictions might result;
- any leases or contractual arrangements, such as agreements for
- renewable energy certificates,
- solar renewable energy certificates, or
- purchasing power; and
- confirming that BorrowerBorrowerPerson who is the obligor per the Note. will not be deemed a public utility.
110.03 | |
|
Requirements
The PCAPCAAssessment of the Property's physical condition and historical operation. must include an evaluation of the Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored… equipment and roofs/structures where the equipment is mounted per the Solar PV Module of Form 4099.
110.04 | |
|
Requirements
When calculating Underwritten NCFUnderwritten NCFNet Cash Flow as adjusted by the Lender per Part II, Chapter 2: Valuation and Income, Section 203: Income Analysis and the applicable products and features in Part III. :
- do not include any income derived from the Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored…, except for tenant utility reimbursement;
- any utility reimbursement income must
- not exceed the trailing 12-month period, and
- consider any decrease from the lower utility expense;
- utility expense must be supported by the trailing 12-month operating history; and
- include all additional Solar PV SystemSolar PV SystemA renewable energy system located on the Property that converts sunlight into electricity and/or a battery storage system containing lithium ion batteries or equivalent technology capable of storing electricity received from the electric grid or a renewable energy system and delivering stored… operating expenses such as:
- operating and maintenance contract fees;
- fixed utility fees;
- incremental real estate taxes;
- insurance coverage; and
- Replacement ReservesReplacement ReservesCustodial Account the Borrower funds during the Mortgage Loan term for Replacements. for equipment replacement and/or system removal and reinstallation upon roof replacement.